I-wall versus T-wall?
This file appears in: London Avenue Canal Levee Breach in 2005

Post Katrina, the repaired breach site of the London Avenue Canal consists of a new flood wall in the T-wall design rather than I-wall design. A T-wall is a reinforced concrete structure supported by foundation pilings with a non-structural steel sheet pile assembly beneath the levee. T-walls are not typically earth supported, are a significantly sturdier design, and are also three or more times more expensive to build than I-walls. Drawing submitted courtesy of Levees.org
This file appears in: London Avenue Canal Levee Breach in 2005
London Avenue Canal Levee Breach in 2005
In 1965, Hurricane Betsy demonstrated that a major hurricane could overtop the earthen levees of the London Avenue Canal. So the Army Corps of Engineers recommended two plans -- raising the height of…